P25 Radio System Implementation Timeline

Event

Detailed Design

Site Improvements / Upgrades

Equipment Production (Round 1)

Factory Assembly & Staging (Round 1)

Equipment Production (Round 2)

Radio System Installation

Fleet Map & Radio Personality Development

Factory Assembly & Staging (Round 2)

Site Optimization

Equipment Production (Round 3)

Factory Assembly & Staging (Round 3)

Cutover Testing

Cutover / Migration

Warranty Period

Start Date

10/1/19

5/4/20

5/26/20

8/19/20

12/24/20

3/15/21

4/15/21

5/11/21

9/17/21

11/10/21

1/26/22

8/31/22

10/10/22

3/8/24

Duration

507 days

470 days 

198 days

80 days 

233 days

433 days

255 days

124 days

458 days

122 days

39 days

244 days

319 days

1095 days